European funds finance asbestos removal from schools in 12 Algarve municipalities
Works were 100% reimbursed
Works were 100% reimbursed
Municipality terminated the contract with the company that was carrying out the works due to "successive delays and non-compliance"
Contractor was in default
Work was carried out by the Chamber
Infraction notices were raised
Works were carried out within the scope of an application by the Municipality to the CRESC Algarve2020 program
Work cost about 412 thousand euros
The start of the school year will not be jeopardized, guarantees the mayor of Beja
The work represents an investment of over 150 thousand euros.
Schools that were transferred to municipal management following the decentralization of competences are being intervened.
Works must be completed before the start of the next school year.